|
Three 16" sewer mains (24" bores) were installed at a
military base in Florida. The bores averaged 420' in length and the
pipe was SDR-17 HDPE, which was butt fused. Depths ranged from 8' to
10' and guidance was provided by the walkover method. The bores were
located in very sensitive areas alongside the base commander's
residence, and other high-ranking officer’s residences.

Installed over 3,000 feet of conduit for power and
communications purposes at the Disney/MGM Studios in Orlando. The
project consisted of pulling (4) 6” conduits in single bores.
This project had a very tight timetable and required seven day work
weeks with all work performed only within specified night hours with
daily restoration to impeccable condition since the work was in an area
normally open to the public. Due to the large number of existing
utilities and limited information about their location Ground
Penetrating Radar was used to verify unknown obstacles. The project was
completed ahead of schedule and we received a commendation from Walt
Disney World for our performance.
Seven, 22" bores totaling 3,000 feet ranging from 75' to
550' were drilled for the installation of a 14" HDPE force main in St.
Augustine, FL. These utility lines were installed at depths ranging
from 4' to 8' along US 1 under intersecting roadways. Walkover guidance
was used for the installations.
Over 3,000 feet of 4" and 8" welded rigid steel conduit
was placed in a series of continuous bores at depths from 8' to 12'.
Bores varied between 200' and 500' in length. At times, both 4" and 8"
conduit was pulled simultaneously. One bore crossed Interstate 95 and a
second bore was completed underneath an earthen on-ramp which was 25'
in vertical height above the ground level at the point at which the
bore crossed underneath.
Approximately 950' of 16" SDR-11 HDPE piping was
installed underneath a wetland area to serve as a new force main line
in Orlando. Guidance was provided by the walkover method.
Fourteen bores consisting of 10,000 feet of 8”
HDPE conduit for a new reuse line were installed for the county along
International Drive. The area was highly congested with pedestrian and
vehicular traffic.
Two 16” HDPE casings containing (4) 4” and
(4) 3” stainless pipes in each casing were installed at the Tampa
International Airport. The bores extended 400 feet with each casing
weighing over 28,000 pounds. The bores were guided through various
critical utilities, including the FAA’s fiber optic
communications cables. Each bore was terminated on the Aircraft
Operational Area. Drilling operations were completed without effecting
operation of the area.
Over 3,000 feet of 6” HDPE conduit was installed
in Kissimmee, Florida. Bore lengths ranged from 50’ to 850’
and were completed using walkover tracking.
ENVIRONMENTAL
APPLICATIONS
Two 240' horizontal wells were installed in continuous
bores at the Department of Energy facility in Florida. The soil vapor
extraction well was placed at 16' below land surface and the
groundwater recovery well was placed at a depth of 26', directly below
the SVE well. The 30' screened intervals were constructed of 4" inside
diameter HDPE and were of a proprietary design constructed by the
client. The shallow well was tracked via the walkover method and the
deep well was installed using a wireline method. Baroid's biodegradable
polymer drill fluid, Bio-bore was used during the boring process.

A 510' groundwater recovery well was placed at a 25'
vertical depth at a hazardous waste site in South Carolina. Well
material was Hydroquest brand slotted and filter wrapped HDPE which was
joined using the heat fusion process. Guidance of the continuous
borehole was accomplished with a wireline system. A mud motor and bent
sub assembly was utilized to bore and steer in the rock formation.
Wells were sealed from the screened interval to the surface with
bentonite.
Three overlapping horizontal wells were installed at 14'
below land surface in continuous boreholes at a manufacturing facility
in Orlando, Florida. The 3 overlapping groundwater recovery wells
created an effective screen length over 700'. Material was 4" schedule
80 PVC .010 slot with a natural sandpack. Guidance was performed by the
walkover guidance method.

Five vapor extraction wells were placed at a depth of 6'
in 5 continuous boreholes under three 200,000 gallon storage tanks at a
Power Plant site in Florida. The 150' to 250' wells were installed
using 6" galvanized metal screen which had welded connections. Guidance
of three of the bores was accomplished using a wireless guidance
system; the other two bores were tracked via the walkover method.
Ground penetrating radar was used to assist in establishing borepaths
due to significant underground obstructions. The wells are part of a
steam injection remediation system. Development consisted of annulus
agitation with water and drill mud breaking fluids in combination with
pumping inside the well screen.

A 410' groundwater recovery well was installed at a
Chemical Plant in Augusta, Georgia. The well material was "Bellend" 4"
schedule 80, slotted PVC. The continuous borehole was drilled to a
vertical depth of 19' utilizing a combination of the walkover method of
tracking early in the borepath and then transistioning to a wireless
guidance system later. Significant interference from a 300,000 volt DC
power source required utilization of the two methods. The riser
sections were sealed with "Benseal", a bentonite based product.
Development consisted of annulus agitation with water and drill mud
breaking fluids in combination with pumping inside the well screen.

A 270' groundwater recovery well was installed with an
130', 8" schedule 80 PVC .010 slot screen section and 10" schedule 80
PVC riser sections which were needed to handle the larger downhole
pumps that were specified. The horizontal portion of the well was
inserted at 35' deep and guidance was provided by the walkover method.
The limited site area, which was located in St. Augustine, Florida,
required a 22 degree entry and exit angles which caused significant
pipe handling complexities during the pullback.
A 145' bore was completed at an active service station
site with petroleum contamination in Tallahassee, Florida. Three 6"
schedule 40 PVC pipes and two 1.5" schedule 80 PVC pipes were installed
simultaneously in the bore. This piping was used to convey vacuum and
air to the vertical wellheads without the need for trenching in front
of the business which would have caused loss in sales for the business
and undue stress on construction crews.
A 500’ horizontal groundwater recovery well was
installed at a chlorine gas manufacturing facility in Augusta, GA. Due
a very strong magnetic field generated by the facility, walkover
equipment was utilized with the wireline guidance tooling to ensure
proper placement of the well screen.
Three 2” HDPE air sparge wells were installed
using the blind bore technique in Orlando, Florida. The 100’
wells were installed at a depth of 40’ below land surface. Due to
the small area of the site, the bores could not be brought out of the
ground as found in a normal drilling project.
Two 4” HDPE recovery wells were installed at a
depth of 40’ below ground surface. The wells were part of a
remedation system to clean-up contaminated groundwater at an old dry
cleaner site in Coral Springs, Florida. The wells were installed using
the blind bore technique with ends of the wells terminating under the
building.
Ten 2” HDPE wells were installed as part of an air
sparge / soil vapor extraction system in Deland, Florida. The 6 air
sparge wells were installed at a depth of 25’ below land surface.
The screen lengths were approximately 200’ in length with total
bore lengths averaging 240’ in length. The 4 vapor extraction
wells were installed at a depth of 15’ below land surface. With
screen and riser lengths mirroring the air sparge wells. All wells were
installed using the blind borehole technique.
Two 6” horizontal wells were re-developed at an
industrial facility in Orlando, Florida. The well screens consisted of
6” carbon steel with vertical slots of .005 inches. The screens
were installed at a depth of 50’ below land surface with screen
lengths of 800’. The wells were cleaned using chemical and
mechanical techniques. Upon completion, flow rates were proven to be
above rates at the time of installation.
Two horizontal wells were installed at a chemical
processing facility in Deer Park, Texas. The wells were constructed of
4” SDR-11 HDPE with a slot size of .010 inches. The wells were
installed at a depth of 40’ below land surface with horizontal
screen segments measuring 750’ and 900’ in length.
One horizontal bio-sparge well was installed under a
large area containing a Fire Department, a US Highway and numerous
residential structures. The well was constructed of 6” SDR-11
HDPE with custom slotting to ensure even air distribution. The well was
installed at a depth of 40’ below land surface. Total well length
was 1,275’ with 850’ of screen.
30 Horizontal wells were installed at a former fueling
site in Gainesville, Florida. 16 Biosparge wells were installed at a
depth of 50 feet BLS with screen lengths 240 to 420 feet in length and
total bore lengths 600-800 feet in length. 14 AS wells were installed
at a depth of 30 feet below land surface with screen lengths 180 to 400
feet in length with total bore lengths 600-800 feet. Both walk over and
wireline tracking were used to complete the installation of the wells.
The wells were 2” SDR 11 HDPE 3408.
|